home bbs files messages ]

Just a sample of the Echomail archive

Cooperative anarchy at its finest, still active today. Darkrealms is the Zone 1 Hub.

   RAILFAN      Trains, model railroading hobby      3,261 messages   

[   << oldest   |   < older   |   list   |   newer >   |   newest >>   ]

   Message 1,939 of 3,261   
   Leroy N. Soetoro to All   
   Special Report Democrat Jerry Browndoggl   
   28 Oct 15 22:15:52   
   
   From: leroysoetoro@usurper.org   
      
   XPost: ca.environment, alt.california, sac.politics   
   XPost: alt.politics.democrats, alt.fan.rush-limbaugh   
      
   http://www.latimes.com/local/california/la-me-bullet-train-cost-final-   
   20151025-story.html   
      
   The monumental task of building California's bullet train will require   
   punching 36 miles of tunnels through the geologically complex mountains   
   north of Los Angeles.   
      
   Crews will have to cross the tectonic boundary that separates the North   
   American and Pacific plates, boring through a jumble of fractured rock   
   formations and a maze of earthquake faults, some of which are not mapped.   
      
   It will be the most ambitious tunneling project in the nation's history.   
      
   State officials say the tunnels will be finished by 2022 — along with 300   
   miles of track, dozens of bridges or viaducts, high-voltage electrical   
   systems, a maintenance plant and as many as six stations. Doing so will   
   meet a commitment to begin carrying passengers between Burbank and Merced   
   in the first phase of the $68-billion high-speed rail link between Los   
   Angeles and San Francisco.   
      
   However, a Times analysis of project documents, as well as interviews with   
   scientists, engineers and construction experts, indicates that the   
   deadline and budget targets will almost certainly be missed — and that the   
   state has underestimated the challenges ahead, particularly completing the   
   tunneling on time.   
      
   "It doesn't strike me as realistic," said James Monsees, one of the   
   world's top tunneling experts and an author of the federal manual on   
   highway tunneling. "Faults are notorious for causing trouble."   
      
   The California High-Speed Rail Authority hasn't yet chosen an exact route   
   through the mountains. It also is behind schedule on land acquisition,   
   financing and permit approvals, among other crucial tasks, and is facing   
   multiple lawsuits. The first construction began in Fresno in July, 21/2   
   years behind the target the rail authority had set in early 2012.   
      
   A confidential 2013 report by the state's main project management   
   contractor, New York-based Parsons Brinckerhoff, estimated that the cost   
   of building the first phase from Burbank to Merced had risen 31% to $40   
   billion. And it projected that the cost of the entire project would rise   
   at least 5%.   
      
   Parsons Brinckerhoff briefed state officials on the estimate in October   
   2013, according to the document obtained by The Times. But the state used   
   a lower cost estimate when it issued its 2014 business plan four months   
   later.   
      
   Jeff Morales, the rail authority chief executive, said he was not aware of   
   the Parsons Brinckerhoff projection. A spokeswoman for the authority   
   declined to discuss the differences in the estimates.   
      
   Public opinion polls taken over the years have shown that support for the   
   project has ebbed as costs have risen — and at $68 billion, the budget is   
   already more than double the $33-billion estimate made by the rail   
   authority before California voters approved bonds for the project seven   
   years ago.   
      
   Morales said he believes the costs can be reduced below the projected $68   
   billion, which includes a 10% contingency. The authority is applying the   
   best construction and engineering methods in the world, and initial   
   contract bids have come in below estimates, he said.   
      
   Morales also said the project can make up for any delays.   
      
   But Bent Flyvbjerg, a University of Oxford business professor and a   
   leading expert on megaproject risk, said the lagging schedule, litigation,   
   growing costs and permit delays arising so early in construction are   
   warning signs that even more delays and higher costs are coming.   
      
   "You have an 80% to 90% probability of a cost overrun on a project like   
   this," Flyvbjerg said. "Once cost increases start, they are likely to   
   continue."   
      
   Flyvbjerg's research found that high-speed rail projects around the world   
   experience an average of 45% cost growth, though 100% increases occur in   
   some cases.   
      
   Although the state hopes to correct some of its early setbacks, the odds   
   are stacked high against it, said Robert Bea, a member of the National   
   Academy of Engineering and a pioneer in civil engineering risk analysis.   
      
   "You can never make up an early cost increase," Bea said. "It just gets   
   worse. I have never seen it go the other way in 60 years."   
      
   Of the challenges facing the bullet train, none is bigger than tunneling.   
      
   Although some large tunnels have been constructed elsewhere without   
   difficulty, including the 3,399-foot Caldecott Tunnel in the Bay Area,   
   others have encountered costly problems.   
      
   The 11-mile East Side Access tunnel in New York City, for example, is 14   
   years behind schedule, and the tab has grown from $4.3 billion to $10.8   
   billion. Boston's 3.5-mile Big Dig was finished in 2007 — nine years   
   behind schedule and at nearly triple the estimated cost.   
      
   Digging stopped on the 2-mile Alaskan Way tunnel under Seattle when a   
   boring machine broke down in December 2013 and had to be retrieved for   
   repairs, causing a multiyear delay with an unknown cost overrun.   
      
   The bullet train will require about 20 miles of tunnels under the San   
   Gabriel Mountains between Burbank and Palmdale, involving either a single   
   tunnel of 13.8 miles or a series of shorter tunnels.   
      
   As many as 16 additional miles of tunnels would stretch under the   
   Tehachapi Mountains from Palmdale to Bakersfield.   
      
   The state will probably opt for twin bores — one for each of two parallel   
   tracks. That means as many as 72 miles of tunneling before 2022.   
      
   Can it meet that schedule?   
      
   "No way," said Leon Silver, a Caltech geologist and a leading expert on   
   the San Gabriel Mountains. "The range is far more complex than anything   
   those people know."   
      
   SIGN UP for the free California Inc. business newsletter >>   
      
   Herbert Einstein, an MIT civil engineer and another of the nation's top   
   tunneling experts, said, "I don't think it is possible."   
      
   "Having looked at a number of these long tunnels, [the California] plan is   
   aggressive," said Einstein, who has consulted on a 35-mile-long tunnel   
   under the Swiss Alps. "From a civil engineering perspective it is very,   
   very ambitious — to put it mildly."   
      
   Thomas O'Rourke, a Cornell University tunnel expert, also has doubts.   
      
   "My first gut reaction is that it is doable, but given the complex geology   
   it is optimistically biased," O'Rourke said. "There are a lot of unknowns.   
   It is going to depend on the complexity of the geology and the ground   
   conditions."   
      
   Monsees, who retired in 2013 from Parsons Brinckerhoff as its senior vice   
   president for tunneling, added, "They are behind and need to get off their   
   rear end and move."   
      
   The rail authority declined to make any of its tunneling engineers   
   available for interviews.   
      
   The pace of tunneling will turn on a handful of factors, including how   
   soon work begins, how fast digging progresses, and the amount of time   
   needed to install track, ventilation, train signals, high-voltage lines   
   and fire-suppression systems.   
      
   Morales said the state does not have a detailed schedule showing how those   
   milestones will be met. He said the task will be left to future   
   contractors.   
      
   Rail officials have said they plan to choose a route and secure   
   environmental approvals for the Burbank-to-Merced line by 2017, at which   
   point the tunneling itself could be put out to bid.   
      
   Bidders then would need time to prepare cost estimates. The only two   
   construction contracts for the project so far were issued more than a year   
   after environmental approvals were in hand.   
      
   After a contract is signed, the contractor can start the process of   
   ordering the enormous, custom-built machines to dig through the mountains.   
   Tunnel boring machines, or TBMs, typically take eight months to a year to   
   build and deliver, said a spokeswoman for Robbins Co., the leading U.S.   
   maker of the machines.   
      
   At that rate, tunneling could begin in 2019 at the earliest.   
      
   TBMs are 300 to 600 feet long and grind circular holes using rotating   
   cutter faces. Staffed by crews of as many as 20, the machines typically   
   operate 20 hours a day, five days a week — with the downtime needed mostly   
   for maintenance and crew changes.   
      
   Once tunneling begins, progress will depend largely on the kind of soil or   
   rock encountered.   
      
   Silver, the Caltech geologist, said the San Gabriels' oldest rocks formed   
   1.7 billion years ago, 200 miles to the south. They became highly   
   fractured as they were shoved north by movements of the Earth's crust.   
      
   Tunnelers will find that rock types change frequently, creating conditions   
   that are among the most challenging for tunneling.   
      
   "If it were one single mass of granite, it would be easy to drill through   
   and provide structural support," said Silver, who trained the Apollo   
   astronauts in lunar geology and pioneered the dating of the San Gabriel   
   Mountains. "But everything in the arc has been bent, shoved, stretched,   
   compressed and metamorphosed."   
      
   The mountain range lies in a giant crescent between two major faults, the   
   San Gabriel and the San Andreas, which separates the Mojave Desert on the   
   North American tectonic plate from the Los Angeles Basin on the Pacific   
   plate.   
      
   Between the two major faults are many secondary faults. Some are vertical   
   strike-slip faults that move laterally, and some are thrust faults that   
   move vertically. Some are horizontal, traveling through the ground at   
   various depths.   
      
   "Every one is going to slow things down tremendously," said Monsees, the   
   former Parsons Brinckerhoff tunnel expert.   
      
   A 2012 report by Parsons Brinckerhoff, obtained by The Times, warned the   
   rail authority that the "seismotectonic complexity ... may be   
   unprecedented" and that the rail route would be crossing faults classified   
   as "hazardous."   
      
   The faults, changes in rock types and shattered rock cause many headaches,   
   sometimes requiring changes in cutter heads. Doing so means stopping the   
   machines while technicians crawl to the front to manually swap out as many   
   as 40 to 60 cutter heads. A full swap of cutter heads can take an eight-   
   hour shift, the engineers said.   
      
   Shattered rock causes additional problems in supporting the overhead   
   formations, requiring workers to bore 10-foot-long holes into the ceiling   
   and insert rock bolts that knit together blocks that weigh tons.   
      
   Morales, the rail agency chief executive, said he did not know what rates   
   of advance will be possible. He said that will be determined by the   
   contractors the state hires.   
      
   In good rock, such as limestone or chalk, TBMs can advance 100 to 200 feet   
   a day. But in fractured mixed rock through fault zones, the advance rates   
   can slow to 10 to 20 feet a day, Einstein of MIT said.   
      
   Einstein's estimate is endorsed by other engineers, including one who has   
   worked closely on the bullet train project and told The Times that 10 feet   
   a day is the likely rate of advance.   
      
   The schedule will depend in part on the number of TBMs and other smaller   
   tunneling machines the state uses, with each machine and its crews adding   
   to costs. The 36 miles of tunnels include a mix of short and long   
   segments, dug by different methods.   
      
   The longest possible tunnel, described as one alternative in state   
   documents, would stretch 13.8 miles under the Angeles National Forest.   
   Assuming TBMs started at both ends and advanced at 20 feet a day for 261   
   days a year, the tunnel would take seven years to complete — finishing in   
   2026. At an advance rate of 10 feet a day, the time would double to 14   
   years.   
      
   The state is considering a different route under the national forest that   
   would instead require a tunnel of just 7 miles. It would take 31/2 to   
   seven years to dig, based on the same advance rates. But that route faces   
   significant political opposition.   
      
   Only after the tunnels are dug can the next phase begin: installing track   
   and other equipment in the 36 underground miles. By way of comparison, the   
   Swiss are taking more than four years after tunneling to install track and   
   equipment in the 35.4-mile-long Gotthard Base Tunnel through the Alps, a   
   project spokesman said. Contractors will take an additional nine months to   
   test the systems.   
      
   The route through the Tehachapi Mountains from Palmdale to Bakersfield,   
   crossing several major faults, is at an even earlier level of planning.   
      
   The last formal analysis was issued more than three years ago. It said   
   that as many as 16 miles of tunnels and as many as a dozen viaducts would   
   be required. The possible routes were later found to be problematic   
   because they are steep and would conflict with a massive wind farm. The   
   agency is working on a new analysis.   
      
   So far, land acquisition has been the biggest cause of delays. The   
   authority owns only a small fraction of the parcels it needs for the 300-   
   mile segment from Burbank to Merced.   
      
   Available financing also has slowed progress. In 2012, the project was   
   running short of cash until federal officials modified a grant agreement   
   and the California Legislature provided additional funding from carbon   
   emission fees.   
      
   The initial operating segment from Burbank to Merced would cost $31   
   billion, according to the rail agency's business plan. Officials have   
   secured $14.7 billion, which leaves the state short by $16.3 billion to   
   build the initial operating segment — not including the 31% cost increases   
   forecast by Parsons Brinckerhoff.   
      
   The rail authority still has not identified sources for about $53 billion   
   to complete the entire Los Angeles-to-San Francisco line.   
      
   State officials are moving ahead without firm financial commitments,   
   contending that private investors will eventually help finance the system.   
   This month, three dozen companies solicited by the state said they are not   
   ready to invest.   
      
   As costs rise, the amount of money the state needs will grow.   
      
   The 2013 Parsons Brinckerhoff cost estimate showed increases in almost   
   every phase of the project. The company reported higher costs for land   
   acquisition, viaducts, tunnels, electrical systems and professional   
   services, largely driven by difficult segments of track that would run   
   through mountains from Palmdale to Bakersfield.   
      
   The document was never made public, and the state rail agency declined a   
   Times request to provide it under the state's public records act. The   
   Times later obtained it from an engineer close to the project.   
      
   Lisa Marie Alley, a spokeswoman for the rail authority, declined to   
   discuss details of the Parsons Brinckerhoff cost estimate, but she said it   
   was "superseded" by the 2014 business plan several months later, which   
   cited the $68-billion estimate.   
      
   The cost estimate was one of two times a key contractor has reported bad   
   budget news that the state rejected.   
      
   Last year, San Francisco engineering firm URS prepared a planning document   
   that projected an increase of 15%, or nearly $1 billion, in the cost of   
   building the line from Bakersfield to Fresno. URS said that it had been   
   "instructed" by the state to hold costs to the same level as 2012 but that   
   the company was refusing to do so.   
      
   The rail authority said later in a rebuttal letter to URS that its   
   statements were misleading and inaccurate. The agency told The Times that   
   the matter was part of a legal dispute that it did not want to publicly   
   discuss. The company no longer has the contract.   
      
   Morales, the authority's chief executive, said he is confident that he can   
   reduce the cost of the project, but he acknowledged that there are no   
   guarantees.   
      
   Nobody can sit here and tell you what something like this is going to cost   
   over a 20-year period.   
   - Jeff Morales, the rail authority chief executive   
   "Nobody can sit here and tell you what something like this is going to   
   cost over a 20-year period," Morales said. "Any big program like this is   
   loaded with challenges. The day you hear me say I am comfortable is the   
   day I am not telling you the truth or the day I have deluded myself."   
      
   After cost projections for the train rose to $98 billion in 2011,   
   vociferous public and political outcry forced rail officials to reassess.   
   They cut the budget to $68 billion by eliminating high-speed service   
   between Los Angeles and Anaheim and between San Jose and San Francisco.   
      
   Morales said that those changes were a normal part of such a big project   
   and that he could not rule out additional changes.   
      
      
      
   --   
   Obama increased total debt from $10 trillion to $19 trillion in the six   
   years he has been in office, and sold out heterosexuals for Hollywood   
   queer liberal democrat donors.   
      
   Barack Obama, reelected by the dumbest voters in the history of the United   
   States of America.  The only American president to deliberately import a   
   lethal infectious disease from Africa, Ebola.   
      
   Loretta Fuddy, killed after she "verified" Obama's phony birth   
   certificate.   
      
   Nancy Pelosi, Democrat criminal, accessory before and after the fact to   
   improper vetting of Barry Soetoro aka Barack Hussein Obama, a confirmed   
   felon using SSAN 042-68-4425, belonging to a dead man.   
      
   Obama ignored the brutal killing of an American diplomat in Benghazi, then   
   relieved American military officers who attempted to prevent said murder   
   in order to cover up his own ineptitude.   
      
   Obama continues his muslim goal of disarming America while ObamaCare   
   increases insurance premiums 300% and leaves millions without health care.   
      
   --- news://freenews.netfront.net/ - complaints: news@netfront.net ---   
      
   --- SoupGate/W32 v1.03   
    * Origin: LiveWire BBS -=*=- UseNet FTN Gateway (1:2320/1)   

[   << oldest   |   < older   |   list   |   newer >   |   newest >>   ]


(c) 1994,  bbs@darkrealms.ca